| February 8, 2008 |
New HABIOS web pages for GCOOS.org web site completed. These include the Proceedings of the HABIOS Plan Development Workshop. |
| February 2008 |
Formation of oversight group for HABIOS web pages. |
| February 2008 |
Version 5 of HABIOS Plan completed; formatted
version sent to all plan reviewers. |
| March 7, 2008 |
Reviewers' comments on version 5 are due
to Susan Martin (srmartin@tamu.edu) |
| March 2008 |
Gulf of Mexico HABIOS Plan I released and
distributed broadly. |
| March 2008 |
Formation of continuing oversight group
for the Gulf HABIOS |
| March/April 2008 |
Decisions made regarding special versions
of the Plan that will be needed. |
| April 2008 |
First cost estimates completed. |